blue-check It is required to extend the construction permit upon delaying commencement time

Official letter No. 2909/BXD-HDXD dated July 26th, 2021 of the Ministry of Construction regarding guidelines on duration of construction permit
Posted: 4/8/2021 7:45:01 AM | Latest updated: 7/8/2021 8:30:44 AM (GMT+7) | LuatVietnam: 5265 | Vietlaw: 527
VietlawOnline

According to clause 1 Article 99 of the Law on Construction No. 50/2014/QH13status2 , before the expiration of the construction permit for construction commencement, if the construction of the works has not commenced yet, the project owner must apply for extension of the construction permit.

The issuance of the construction permit, including extension and re-issuance of construction permit, with regard to special-grade construction works belongs to competence of provincial-level People’s Committees (clause 37 Article 1 and point c clause 2 Article 3 of Law No. 62/2020/QH14 ).

In addition, the project owner shall pay attention to carry out procedures for notifying construction commencement and perform responsibilities and obligations in the course of construction as regulated at clause 2 Article 55 and Article 56 of Decree No. 15/2021/ND-CP .

Ms Phuong Thao (VietlawOnline.com)
Please tag VietlawOnline.com when reposting this article

Related documents

Penalty document

Unknown

Information

Effective Date Unknown
ExpiredDate Unknown
Published Vietlaw's Newsletter No. 527

Files attachment

enflag pdficon CV2909_26072021BXD[VLO].pdf

Timeline

No data

Construction

blue-check Issue relating to payment for warranty of construction works
blue-check From August 8th, 2022: Fee for grade adjustment to certificate of construction capacity shall be increased to 1,000,000 VND
blue-check It is required to ensure the net building density for construction of factories not exceeding 70%
blue-check
blue-check Issue relating to completion of construction works
blue-check Regarding application of foreign standards to construction works in Vietnam
blue-check How to calculate costs for making feasibility study report and construction design costs
blue-check Regarding regulations on calculation of costs of appraisal of construction projects
blue-check Some notes upon liquidation of a construction contract due to the contractor’s breach in the contract
blue-check Regarding modification of categories, origin in a construction contract
blue-check Order of priority application of documents enclosed with a construction contract
blue-check Investor has the right to unilaterally terminate the contract if the contractor delays construction work for 56 consecutive days
blue-check A Joint Stock Company with less than 50% state capital shall not comply with the Law on public investment
blue-check Regarding construction permit for construction of works in industrial clusters
blue-check Requirements upon making fire prevention and fighting designing for works according to foreign standards
blue-check Criteria for structures permitted for construction in HCMC amid Covid-9
blue-check Construction norms applicable from October 15th, 2021
blue-check New methods for determination of construction investment costs
blue-check Regulations on management of occupational safety and health of construction projects
blue-check Regarding application of foreign standards in construction activities in Vietnam