blue-check Investor has the right to unilaterally terminate the contract if the contractor delays construction work for 56 consecutive days

Official letter No. 361/BXD-KTXD dated February 9th, 2022 of the Ministry of Construction regarding guidelines for construction contract
Posted: 30/3/2022 2:09:18 PM | Latest updated: 1/4/2022 6:42:04 AM (GMT+7) | LuatVietnam: 5422
VietlawOnline

According to point b clause 7 Article 41 of Decree No. 37/2015/ND-CPstatus2 , the employer (investor) has the right to unilaterally terminate the contract if in 56 consecutive days the contractor fails to execute the construction work under the contract that results in violations of the contract progress as agreed in the contract, except otherwise as approved by the employer.

Ms Phuong Thao (VietlawOnline.com)
Please tag VietlawOnline.com when reposting this article
Related documents
Not found
Penalty document
Unknown
Information
Effective Date Unknown
ExpiredDate Unknown
Files attachment
enflag pdficon CV361-09022022BXD[VLO].pdf
Timeline
No data

Construction